Rotkreuz / Küssnacht, 23.05.2025

Night-time lane reductions on the A4 motorway

In order to ensure operations over the next 15 to 20 years, the Federal Roads Office (Astra) is repairing the motorway section between the Rütihof junction and the Küssnacht junction in three stages between 2025 and 2027.

The road surfaces along the entire stretch will be replaced with low-noise surfaces and the crash barriers, fences and operating and safety equipment will be renewed.

Due to conversion work, the A4 southbound carriageway will only have one lane on two nights               Image: Google Maps

 

According to a statement from Astra, the changeover work from Construction Phase 1 (work in the area of the central reservation) to Construction Phase 2 will begin on Friday evening. The changeover will require lane closures in the direction of Altdorf on the following two nights.

 

During Construction Phase 2, which is expected to last until mid-August 2025, work will take place on the carriageway in the direction of Altdorf. From mid-August to mid-November, construction work will take place on the other side in the direction of Zurich. During the day, traffic will be guided in two lanes in both directions for the entire construction period.